FW: One Warrington Gardens URN Ref - Weekly Update 21.03.2024

WBM info at wb19.co.uk
Fri Mar 22 15:46:03 GMT 2024


Good afternoon everyone,
Please find below the weekly update from the project coordinator who is dealing with the building cladding.


As part of our role as project coordinator, we will send out weekly updates to the applicant to advise where we are in the process and what happens next.
 Any actions that need to be completed are highlighted in red.
 Also, please note that I am on annual leave between 2nd and 4th April.  I will not be contactable by phone but will check emails periodically and will respond to anything urgent over this period.

Please ensure that this update is sent to the managing agent who are to distribute to the wider leaseholder/resident community to ensure that all relevant parties are kept up to date with progress, in line with application requirements and code of conduct.

Application Submission Status
The application to the Building Safety Fund has numerous stages, which are outlined below.  Please refer to the below explanations in order to identify where we are in the process and what will happen next.


  1.  Eligibility

This is the initial stage and involves completing the initial eligibility submission, we are required to answer a 70 point online application.  These responses have been collated and confirmed as correct with the board and have been uploaded to the eligibility portal along with supporting documents, including the FRAEW, images of the building and confirmation of the height of the building.  Eligibility has been confirmed and we have been granted access to the DLUHC portal allowing us to make an application for funding.

  1.  Stage 1 – legal due diligence

This involves submitting details of the building, the lease, and the legal set up to establish whether the building is eligible legally to receive funding.   Stage 1 information is completed and has been submitted.  The CSS has acknowledged receipt and is completing their review process.  I have asked the CSS to confirm some timelines as to when we can expect this to be complete and I will update once I have some further details on this point.

  1.  Pre-tender support

In order to carry out a full contract tender submission (as required by the BSF), we will apply for advance funding, known as pre-tender support or PTS.  The applicant is required to submit an estimate of costs for the project and advise the BSF how much money we will need now to progress the project to final approval.   There have recently been changes within the BSF as to how PTS is calculated and as such the requirements for this stage may well change in the coming weeks.

  1.  Stage 2 application – full works and costs

As soon as the PTS funding has been received, the applicant will instruct a project manager to proceed with a competitive tender.  This will likely take 3 months at least and will provide at the end a fully itemised works programme along with project costs.  This will be submitted to the GLA and reviewed internally, along with various appointment documents and key project information.  Once the GLA are satisfied with the information they have received, the project will be passed to a cost consultant for final approval.  The cost consultant is appointed on behalf of the BSF and is the party with the full and final authority to determine the funding that will be awarded to us.

  1.  FAB Approval

Once the GLA and cost consultant have interrogated the tender submission and stage 2 application, the project will be passed to DHLUC who will give the final approval at a Financial Approval Board meetings, which are held every fortnight.

  1.  Signing of Legal Documents

Once final FAB approval has been received, we will be provided with a set of documents which will need to be completed to allow the BSF to release funding to us.  We will work closely with solicitors at this stage to ensure that the legal documents are completed correctly.

  1.  Final accounts

At the end of the project, we will submit final accounts to the BSF and receive a final balancing payment to close out the project.



Next Steps

The following steps are to be completed in the coming week.

  1.  Wait for CSS to complete stage 1 review


Advice and Guidance
If you have any queries relating to your building, please revert to your property manager in the first instance.  However, there are also government agencies and independent advice groups who are available to assist leaseholders.  Please use the links below to access these services.

Home - The Leasehold Advisory Service (lease-advice.org)<https://www.lease-advice.org/>
Leaseholder and resident information on the Cladding Safety Scheme (CSS) - GOV.UK (www.gov.uk)<https://www.gov.uk/guidance/leaseholder-and-resident-information-on-the-cladding-safety-scheme-css>
Information for leaseholders and other residents on fire safety and remediation<https://www.gov.uk/guidance/information-for-leaseholders-and-other-residents-on-fire-safety-and-remediation-of-historic-building-safety-defects>

Kind regards,

Kiara Long   BSc (hons), MIRPM, QInstPa
Consultant – Cladding Remediation Lead

email - kiara at itboxadvisory.co.uk<mailto:kiara at itboxadvisory.co.uk>
mobile – 07584 788 484
web - www.insidetheboxadvisory.co.uk<http://www.insidetheboxadvisory.co.uk/>
address - The Harley Building, 77 New Cavendish Street, London W1W 6XB

[cid:ii_18e62600da84cff311]

The information contained in this message may be CONFIDENTIAL and is intended for the addressee only. Any unauthorised use, dissemination of the information, or copying of this message is prohibited. Please check for viruses before accessing attachments. Although we endeavour to keep files clean, we can take no responsibility for any damage cause by contagion. If you are not the addressee, please notify the sender immediately by return email and delete this message. Although this email and any attachments are believed to be free of any virus, or other defect which might affect any computer or system into which they are received and opened, it is the responsibility of the recipient to ensure that they are virus free and no responsibility is accepted by Inside the Box Advisory Ltd for any loss or damage from receipt or use thereof. Please note that all email messages are subject to interception for lawful business purposes.



Kind regards,

Lynette


Westbourne Management
9 Spring St, London W2 3RA

Office:  0203 987 5050
Email:    lynette at wb19.co.uk<mailto:lynette at wb19.co.uk>

[cid:image001.png at 01DA7C70.08986F40]<https://www.wb19.co.uk/>

[cid:image002.png at 01DA7C70.08986F40]<http://www.rics.org/uk/>                   [IRPM_Member_Logo_v1_CMYK.JPG] <https://www.irpm.org.uk/public/home>                [IRPM_Member_Logo_v1_CMYK_25%.jpg] <https://www.tpos.co.uk/>                  [A picture containing text, clipart  Description automatically generated] <https://www.linkedin.com/company/westbourne-block-management>

This email is confidential and may contain privileged or copyright information. If you are not the intended recipient please delete this email and you are notified that disclosing, copying, distributing or taking any action in reliance on the contents of this information is strictly prohibited. Any views or opinions presented in this email are solely those of the author and do not necessarily represent those of the company. Westbourne Block Management Limited, Registered in England and Wales, company number 08775318.  VAT Registration Number 177 4688 53.  All Rights Reserved.  Regulated by RICS.


-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20240322/eab4ee09/attachment.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 46648 bytes
Desc: image001.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20240322/eab4ee09/attachment.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 56227 bytes
Desc: image001.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20240322/eab4ee09/attachment-0001.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 8303 bytes
Desc: image002.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20240322/eab4ee09/attachment-0002.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image003.jpg
Type: image/jpeg
Size: 8837 bytes
Desc: image003.jpg
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20240322/eab4ee09/attachment.jpg>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image004.png
Type: image/png
Size: 10970 bytes
Desc: image004.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20240322/eab4ee09/attachment-0003.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image005.png
Type: image/png
Size: 1420 bytes
Desc: image005.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20240322/eab4ee09/attachment-0004.png>


More information about the Family mailing list