FW: FW: One Warrington Gardens URN Ref - Weekly Update 14.11.2024
Oliver Sampson-Bancroft
oliver at wb19.co.uk
Fri Nov 15 09:49:53 GMT 2024
Good morning everyone,
Please find below the latest update from the project coordinator who is dealing with the building cladding.
Best regards,
Oliver Sampson-Bancroft
Westbourne Management
9 Spring St, London W2 3RA
Office: 0203 987 5050
Direct: 0203 987 5053
Email: oliver at wb19.co.uk<mailto:oliver at wb19.co.uk>
[A logo with buildings and text Description automatically generated]<https://www.wb19.co.uk/>
[cid:ii_1932bfc4327692e333]<http://www.rics.org/uk/> [A logo with blue text Description automatically generated] <https://www.tpi.org.uk/> [cid:image002.jpg at 01DB3743.B6F779D0] <https://www.tpos.co.uk/> [A picture containing text, clipart Description automatically generated] <https://www.linkedin.com/company/westbourne-block-management>
This email is confidential and may contain privileged or copyright information. If you are not the intended recipient please delete this email and you are notified that disclosing, copying, distributing or taking any action in reliance on the contents of this information is strictly prohibited. Any views or opinions presented in this email are solely those of the author and do not necessarily represent those of the company. Westbourne Block Management Limited, Registered in England and Wales, company number 08775318. VAT Registration Number 177 4688 53. All Rights Reserved. Regulated by RICS.
From: Kiara Long <kiara at itboxadvisory.co.uk<mailto:kiara at itboxadvisory.co.uk>>
Sent: 14 November 2024 15:36
To: OWG Board <owgboard at gmail.com<mailto:owgboard at gmail.com>>; Luke Thatcher <luke at harrisassociatesuk.com<mailto:luke at harrisassociatesuk.com>>; Oliver Sampson-Bancroft <oliver at wb19.co.uk<mailto:oliver at wb19.co.uk>>
Subject: One Warrington Gardens URN Ref - Weekly Update 14.11.2024
Dear All,
As part of our role as project coordinator, we will send out weekly updates to the applicant to advise where we are in the process and what happens next.
Any actions that need to be completed are highlighted in red. @Oliver Sampson-Bancroft<mailto:oliver at wb19.co.uk>, I have included you within the this email as I will be sending these on a weekly basis as a leaseholder update – but please do speak to @OWG Board<mailto:owgboard at gmail.com> for approval before sharing this with the leaseholders.
Please ensure that this update is sent to the wider leaseholder/resident community to ensure that all relevant parties are kept up to date with progress, in line with application requirements and code of conduct.
Application Submission Status
The application to the Building Safety Fund has numerous stages, which are outlined below. Please refer to the below explanations in order to identify where we are in the process and what will happen next.
1. Eligibility
This is the initial stage and involves completing the initial eligibility submission, we are required to answer a 70 point online application. These responses have been collated and confirmed as correct with the board and have been uploaded to the eligibility portal along with supporting documents, including the FRAEW, images of the building and confirmation of the height of the building. Eligibility has been confirmed and we have been granted access to the DLUHC portal allowing us to make an application for funding.
1. Stage 1 – legal due diligence
This involves submitting details of the building, the lease, and the legal set up to establish whether the building is eligible legally to receive funding. Stage 1 approval has been confirmed and this section is complete. We are now waiting for the letter confirming the approval.
1. Pre-tender support
In order to carry out a full contract tender submission (as required by the BSF), we will apply for advance funding, known as pre-tender support or PTS. The applicant is required to submit an estimate of costs for the project and advise the BSF how much money we will need now to progress the project to final approval. There have recently been changes within the BSF as to how PTS is calculated and as such the requirements for this stage may well change in the coming weeks.
The GLA have confirmed that the PTS has been awarded in the amount of £340,170 including VAT. We have provided the GLA with all the information they need to set up out account and make the payment. I have chased with Funmi (GLA contact) to find out where they are in that process and she has confirmed that the account has not been finalised by the GLA yet. I have chased again this week and Funmi has advised that they are still completing their internal processes.
Funmi has also asked for confirmation on which funding payment schedule we would like to use. I have attached the email that I sent on this matter. Please let me know if you have any questions on this query.
1. Stage 2 application – full works and costs
As soon as the PTS funding has been received, the applicant will instruct a project manager to proceed with a competitive tender. This will likely take 3 months at least and will provide at the end a fully itemised works programme along with project costs. This will be submitted to the GLA and reviewed internally, along with various appointment documents and key project information. Once the GLA are satisfied with the information they have received, the project will be passed to a cost consultant for final approval. The cost consultant is appointed on behalf of the BSF and is the party with the full and final authority to determine the funding that will be awarded to us.
Holly has provided some template legal documents to be reviewed in advance of moving to stage 2. Edwin Coe have been appointed to act as solicitors for this project.
Once PTS payment has been received, I will advise Luke who will be able to commence the tender process.
1. FAB Approval
Once the GLA and cost consultant have interrogated the tender submission and stage 2 application, the project will be passed to DHLUC who will give the final approval at a Financial Approval Board meetings, which are held every fortnight.
1. Signing of Legal Documents
Once final FAB approval has been received, we will be provided with a set of documents which will need to be completed to allow the BSF to release funding to us. We will work closely with solicitors at this stage to ensure that the legal documents are completed correctly.
1. Final accounts
At the end of the project, we will submit final accounts to the BSF and receive a final balancing payment to close out the project.
Next Steps
The following steps are to be completed in the coming week.
1. GLA to provide pre-tender support payment
2. Confirm the payment schedule.
Advice and Guidance
If you have any queries relating to your building, please revert to your property manager in the first instance. However, there are also government agencies and independent advice groups who are available to assist leaseholders. Please use the links below to access these services.
Home - The Leasehold Advisory Service (lease-advice.org)<https://www.lease-advice.org/>
Leaseholder and resident information on the Cladding Safety Scheme (CSS) - GOV.UK (www.gov.uk)<https://www.gov.uk/guidance/leaseholder-and-resident-information-on-the-cladding-safety-scheme-css>
Information for leaseholders and other residents on fire safety and remediation<https://www.gov.uk/guidance/information-for-leaseholders-and-other-residents-on-fire-safety-and-remediation-of-historic-building-safety-defects>
Kind regards,
Kiara Long BSc (hons), MIRPM, QInstPa
Consultant – Cladding Remediation Lead
email - kiara at itboxadvisory.co.uk<mailto:kiara at itboxadvisory.co.uk>
mobile – 07584 788 484
web - www.insidetheboxadvisory.co.uk<http://www.insidetheboxadvisory.co.uk/>
address - The Harley Building, 77 New Cavendish Street, London W1W 6XB
[cid:ii_1932bfc43274cff311]
The information contained in this message may be CONFIDENTIAL and is intended for the addressee only. Any unauthorised use, dissemination of the information, or copying of this message is prohibited. Please check for viruses before accessing attachments. Although we endeavour to keep files clean, we can take no responsibility for any damage cause by contagion. If you are not the addressee, please notify the sender immediately by return email and delete this message. Although this email and any attachments are believed to be free of any virus, or other defect which might affect any computer or system into which they are received and opened, it is the responsibility of the recipient to ensure that they are virus free and no responsibility is accepted by Inside the Box Advisory Ltd for any loss or damage from receipt or use thereof. Please note that all email messages are subject to interception for lawful business purposes.
-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20241115/a8e2f61c/attachment-0001.htm>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 46648 bytes
Desc: image001.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20241115/a8e2f61c/attachment-0005.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.png
Type: image/png
Size: 56227 bytes
Desc: image002.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20241115/a8e2f61c/attachment-0006.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image003.png
Type: image/png
Size: 8303 bytes
Desc: image003.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20241115/a8e2f61c/attachment-0007.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image006.png
Type: image/png
Size: 1420 bytes
Desc: image006.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20241115/a8e2f61c/attachment-0008.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image001.png
Type: image/png
Size: 21198 bytes
Desc: image001.png
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20241115/a8e2f61c/attachment-0009.png>
-------------- next part --------------
A non-text attachment was scrubbed...
Name: image002.jpg
Type: image/jpeg
Size: 163827 bytes
Desc: image002.jpg
URL: <http://fabris.co.uk/pipermail/family_fabris.co.uk/attachments/20241115/a8e2f61c/attachment-0001.jpg>
More information about the Family
mailing list